Energy-from-Waste Facility
Covanta Huntsville, Inc.
Huntsville, Alabama
The Huntsville Solid Waste to Energy Facility, operating as Covanta Huntsville, Inc., is located on 20.5 acres adjacent to Redstone Arsenal in Huntsville, AL. Covanta Huntsville began commercial operation in July 1990. The facility processes 690 tons per day of solid waste and sewage sludge from the Huntsville wastewater treatment plant. Covanta Huntsville produces nearly 180,000 pounds of steam per hour, which travels through a six-mile long export line for the arsenal's heating and air conditioning needs. The facility is equipped with four fossil-fuel package boilers which allow steam to be available 100 percent of the time. The facility is also equipped to burn biogas from a nearby landfill.
Technical Data
Facility Address:
5251 Triana Boulevard
Huntsville, AL 35805
(256) 882-1019
Site:
20.5 acres owned by the Huntsville Solid Waste Disposal Authority
Commercial Operation:
July 17, 1990
Energy-from-Waste System:
Two 365 ton-per-day waterwall furnaces with Martin® reverse-reciprocating grates and ash handling system
Boiler Design:
350 pounds per square inch gauge (psig)/470°F superheater outlet conditions
Air Pollution Control Equipment:
Semi-dry flue gas scrubbers injecting lime, fabric filter baghouses, nitrogen oxide control system, mercury control system, and continuous emissions monitoring (CEM) system
Rated Refuse Capacity:
690 tons per day
Energy Generation @ Rated Capacity:
89,310 lbs. of steam per hour each refuse unit; 100,000 lbs. per hour from each of four oil and gas fired package boilers; total of 400,000 lbs. per hour rated capacity of steam transmission line.
Sold to:
United States Army's Redstone Arsenal; steam used for heating and air conditioning.